QuantLib returns 日期超出范围的付款时间表?
QuantLib returns payment schedules with date outside the bound?
我正在使用 QuantLib 1.7.1 并尝试 运行 这些代码:
Date begin(30, September, 2009), end(15, Jun, 2012);
Calendar myCal = Japan();
BusinessDayConvention bdC = BusinessDayConvention(Following);
Period myTenor(6, Months);
DateGeneration::Rule myRule = DateGeneration::Forward;
Schedule mySched(begin, end, myTenor, myCal, bdC, bdC, myRule, true);
std::vector <Date > finalSched = mySched.dates();
BOOST_FOREACH(Date d, finalSched) std::cout << d << std::endl;
我希望得到一个下限和上限分别为 30/9/2009 和 15/6/2012 的时间表,如下所示:
September 30th, 2009
March 31st, 2010
September 30th, 2010
March 31st, 2011
September 30th, 2011
March 30th, 2012
June 15th, 2012
但我得到的结果是最终付款日期是 29/6/2012,这是在我设置的范围之后:
September 30th, 2009
March 31st, 2010
September 30th, 2010
March 31st, 2011
September 30th, 2011
March 30th, 2012
June 29th, 2012
如果我将 DateGeneration 规则设置为 Backward,它将按预期工作(计划下限为 30/9/2009):
September 30th, 2009
December 15th, 2009
June 15th, 2010
December 15th, 2010
June 15th, 2011
December 15th, 2011
June 15th, 2012
QuantLib 是故意在第一种情况下给出超出范围的结果还是这是一个错误?
据我所知,您传递的最后一个参数 (true
) 导致所有日期都调整为业务月末,包括到期日,即使离到期日还很远那个日期。我不确定这是怎么发生的,但我不认为这是预期的。
截至目前,恐怕还没有针对此特定案例的解决方法。将 false
作为最后一个参数传递会产生正确的成熟度,但不会调整两者之间的日期:
September 30th, 2009
March 30th, 2010
September 30th, 2010
March 30th, 2011
September 30th, 2011
March 30th, 2012
June 15th, 2012
所以如果你碰巧需要这种特殊的联系,它对你没有帮助。
此外,只有当开始日期是该月的最后一个工作日时才会发生这种情况;如果不是,则忽略传递的 endOfMonth
参数。
简而言之,是的:这可能是一个错误。
更新: 实际上,有一个我忘记的解决方法:您可以通过传递 Unadjusted
作为终止日期约定:
Schedule mySched(begin, end, myTenor, myCal, bdC, Unadjusted, myRule, true);
这会产生您期望的日期:
September 30th, 2009
March 31st, 2010
September 30th, 2010
March 31st, 2011
September 30th, 2011
March 30th, 2012
June 15th, 2012
不过,我仍然倾向于将其他行为视为某种错误,因为它太出乎意料了。
我正在使用 QuantLib 1.7.1 并尝试 运行 这些代码:
Date begin(30, September, 2009), end(15, Jun, 2012);
Calendar myCal = Japan();
BusinessDayConvention bdC = BusinessDayConvention(Following);
Period myTenor(6, Months);
DateGeneration::Rule myRule = DateGeneration::Forward;
Schedule mySched(begin, end, myTenor, myCal, bdC, bdC, myRule, true);
std::vector <Date > finalSched = mySched.dates();
BOOST_FOREACH(Date d, finalSched) std::cout << d << std::endl;
我希望得到一个下限和上限分别为 30/9/2009 和 15/6/2012 的时间表,如下所示:
September 30th, 2009
March 31st, 2010
September 30th, 2010
March 31st, 2011
September 30th, 2011
March 30th, 2012
June 15th, 2012
但我得到的结果是最终付款日期是 29/6/2012,这是在我设置的范围之后:
September 30th, 2009
March 31st, 2010
September 30th, 2010
March 31st, 2011
September 30th, 2011
March 30th, 2012
June 29th, 2012
如果我将 DateGeneration 规则设置为 Backward,它将按预期工作(计划下限为 30/9/2009):
September 30th, 2009
December 15th, 2009
June 15th, 2010
December 15th, 2010
June 15th, 2011
December 15th, 2011
June 15th, 2012
QuantLib 是故意在第一种情况下给出超出范围的结果还是这是一个错误?
据我所知,您传递的最后一个参数 (true
) 导致所有日期都调整为业务月末,包括到期日,即使离到期日还很远那个日期。我不确定这是怎么发生的,但我不认为这是预期的。
截至目前,恐怕还没有针对此特定案例的解决方法。将 false
作为最后一个参数传递会产生正确的成熟度,但不会调整两者之间的日期:
September 30th, 2009
March 30th, 2010
September 30th, 2010
March 30th, 2011
September 30th, 2011
March 30th, 2012
June 15th, 2012
所以如果你碰巧需要这种特殊的联系,它对你没有帮助。
此外,只有当开始日期是该月的最后一个工作日时才会发生这种情况;如果不是,则忽略传递的 endOfMonth
参数。
简而言之,是的:这可能是一个错误。
更新: 实际上,有一个我忘记的解决方法:您可以通过传递 Unadjusted
作为终止日期约定:
Schedule mySched(begin, end, myTenor, myCal, bdC, Unadjusted, myRule, true);
这会产生您期望的日期:
September 30th, 2009
March 31st, 2010
September 30th, 2010
March 31st, 2011
September 30th, 2011
March 30th, 2012
June 15th, 2012